Taishan nuclear ‘leak threat’ fallout a new headache for China

Nuclear safety authorities dismissed the incident at the southern Guangdong plant as a ‘common phenomenon’ but, whatever happened, its going to be that bit harder now for Beijing to make the case for atomic power to its people. So what actually happened?


The joint Sino-French Taishan Nuclear Power Station being built outside the city of Taishan in Guangdong province. Photo: AFP

Nuclear safety authorities dismissed the incident at the southern Guangdong plant as a ‘common phenomenon’ but, whatever happened, its going to be that bit harder now for Beijing to make the case for atomic power to its people. So what actually happened?

 

French energy company EDF is continuing to investigate a potential issue linked to a build-up of inert gases at its nuclear plant in China’s southeastern province of Guangdong.

The probe comes after CNN reported that the US government was assessing a report of a leak at the Taishan power station. The report was made by Framatome, the EDF business that designed the plant’s reactor and remains involved in its operations.

Also on AF: What will it be like when the Chinese bounceback passes its peak?

Framatome warned that the plant, a joint venture with China General Nuclear Power Group (CGN) that is located around 200 kilometres from Hong Kong, was facing an “imminent radiological threat”.

Here is what we know so far.

WHAT HAPPENED AT TAISHAN?

According to CNN, U.S. officials have been investigating the Framatome claims of a leak for the past week.

EDF, which has a minority stake in the plant, said a build-up of krypton and xenon – both inert gases – had affected the primary circuit of Taishan Unit 1, but added that it was a “known phenomenon, studied and provided for in the reactor operating procedures”.

Majority owner CGN also said in a statement that operations at the plant met safety rules.

Radiation levels in the vicinity were still normal on Monday, according to real-time data from the National Nuclear Safety Administration (NNSA).

According to CNN, Framatome’s warning included an accusation that NNSA was raising acceptable radiation limits outside the Taishan plant to avoid having to shut it down.

Foreign ministry spokesman Zhao Lijian told reporters in a regular briefing the plant was fully compliant with all requirements and operating normally.

WHAT ARE THE RISKS?

Nuclear experts have generally played down the risks. CNN cited US officials as saying that the dangers to the public were currently minimal.

Li Ning, a Chinese nuclear scientist based in the United States, told Reuters that CNN was “making a mountain out of a molehill” and that it was unrealistic to expect “zero failure” in the fuel cladding of nuclear projects anywhere in the world.

Li said the media were “often unwilling to put risks into proper perspective”, which he said had effectively killed off the nuclear industry in the west.

“Coal-fired power plants can emit and discharge more radioactivity than nuclear power plants,” Li said.   

WHY IS THE US GOVERNMENT INVOLVED?

CGN, China’s largest state-owned nuclear company, was placed on a US blacklist in August 2019 for allegedly making efforts to acquire advanced US technology and material for diversion to military uses in China.

That means that Framatome, which has operations in the United States, would need a waiver from the US government to allow it to help CGN fix technological problems, Li said.

China’s foreign ministry has said the blacklist is a misuse of export control measures.

WHAT IS TAISHAN’S SAFETY RECORD?

Minor safety issues have been quite frequent at Taishan. In March, inspectors checking a faulty voltmeter in Unit 1 accidentally caused an electrical malfunction that triggered an automatic shutdown, according to NNSA incident records.     

In April, a burst of radioactive gas unexpectedly entered a pipe at Unit 1’s waste gas treatment system just as workers were trying to seal it, also triggering an alarm, NNSA said.

WHAT IS AN “EPR”?

Formerly known as a “European Pressurised Reactor”, the EPR is a “third-generation” nuclear technology that includes enhanced safety features as well as greater generation capacity.

It was designed by Framatome together with Germany’s Siemens. Its third-generation rivals now include Westinghouse’s AP1000, Russia’s VVER-1200 and China’s Hualong One.

In 2006, EDF and fellow French nuclear group Areva lost a bid to build four reactors on China’s eastern coast, with China opting for Westinghouse’s model after signing a deal to transfer core technology for use in its own projects.

In 2007, EDF agreed to build two EPRs at Taishan, which would be 70%-owned by CGN. Construction got underway in 2010. Originally scheduled to be connected to the grid within four years, the first unit wasn’t completed until December 2018.

WHAT NEXT?

EDF did not provide a timeframe for completion of its investigation, nor did US officials, according to the CNN report.

Problems at the Taishan project are unlikely to dent China’s nuclear ambitions, but they underscore the challenges facing foreign reactor developers in a market increasingly dominated by domestic players.

China fell short on its 2020 nuclear capacity target. Many complained the sector’s expansion was derailed not only by the 2011 Fukushima disaster, but also by the lengthy delays and spiralling costs at foreign-designed projects.

As it steps up the construction of new plants, China is now expected to depend primarily on its own third-generation Hualong One design, but it is also helping to finance the construction of an EPR project at Britain’s Hinkley Point.      

 

  • Reporting by Reuters

 

Read more:

India-UK open cleantech two-way street of investment, green opportunity

Trouble brewing in Aussie solar sector, but some stay the course

 

Sean O'Meara

Sean O'Meara is an Editor at Asia Financial. He has been a newspaper man for more than 30 years, working at local, regional and national titles in the UK as a writer, sub-editor, page designer and print editor. A football, cricket and rugby fan, he has a particular interest in sports finance.